Hey folks,
When generating a "Dependencies Report" as part of a "Plan", Jira appears to only show issues with certain link types ("blocks", "relates to", "is dependency of" etc.). Whereas others (e.g. "breaks into") are not shown, which means only a subset of dependent issues are displayed in the Dependency Report.
Is this a known issue? And if so, is there any way to fix it?
Hi there!
Sorry I'm a few years late! You know how it is...
Try going to Cog → Manage Apps and look for a setting called Dependencies
From there, you should be able to change the Dependency settings which will allow you to add more link types