Sprint Burndown Chart - Remaining Values

Brent Hetland
Contributor
January 18, 2019

Hi,

Why do the "Remaining Values" not update, until I move a Task to "Done" status?

If I have a task that is initially estimated to take 16 hours, and then I set the status to "In Progress", log 4 hours on it one day, log 3 hours on it the next day, I'd expect the Burndown chart "Remaining Hours" to reflect the 4 hours and 3 hours. But it doesn't.

It doesn't reflect the hours logged, until I change the status to Done.

That makes no sense, since all of my tasks in a sprint could be "In Progress" with just an hour work remaining, yet the burndown chart would show all of their original estimate time remaining.

Perhaps something needs to be configured differently for it to work the way it should???

Thanks, Brent

2 answers

1 accepted

0 votes
Answer accepted
Taranjeet Singh
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 18, 2019

@Brent Hetland You may not have selected the Estimation and Tracking Statistic correctly in your JIRA project for your use case. Please refer to this Atlassian document to see how you need to set them so that when you log time on your issues, then the Burndown chart shows the partial burndown (the number of hours currently used and remaining each day): 

https://confluence.atlassian.com/jirasoftwarecloud/configuring-estimation-and-tracking-764478030.html

Brent Hetland
Contributor
January 18, 2019

Thanks! That is what I was looking for.

Sorry for the novice-level question! I'm not the Admin of the board and we've just started using it...

Best Regards, Brent

Like Alain MAIL likes this
0 votes
Judy Colonero
Contributor
September 24, 2019

I have a similar scenario:

 

On the burndown report for TP-60 it shows there is 2d 7h 15m remaining. 

On the actual story:  Estimated = 5h, Logged 4h, Remaining 1h -- this is correct.  

 

How can the report show that there is 2d+ remaining.  This is misleading to management who periodically reviews the sprint burndown report.  

 

It also states in the Event Detail of the Sprint Report:

"Remaining Time Estimate changed from 5h to 1h".

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events