Removing unscheduled version

Arthur Maltson
Contributor
August 18, 2011

We've recently started using GreenHopper in our organization. We're putting all issues in the backlog version and then pulling them into each iteration. I'm finding that we never use the "Unscheduled" version and I was wondering if there was a way to remove it. Thank you in advance.

2 answers

1 accepted

1 vote
Answer accepted
Nicholas Muldoon
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 18, 2011

Hi Arthur,

There is no way to remove Unscheduled, it will remain there and display any issues that are not raised in a Fix Version.

Thank you.

Regards,
Nicholas Muldoon

Arthur Maltson
Contributor
August 18, 2011

Thanks Nicholas. Are there any plans to allow setting a default Fix Version (say to Product Backlog) and having the ability to remove Unscheduled?

0 votes
Nicholas Muldoon
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 19, 2011

No plans at this stage Arthur. It is the first time I recall hearing a request for this feature. Feel free to add it to the backlog:

http://jira.atlassian.com/browse/GHS

Thanks Arthur,

Nicholas

Arthur Maltson
Contributor
August 22, 2011

Thanks, created a JIRA issue here: https://jira.atlassian.com/browse/GHS-3562

Suggest an answer

Log in or Sign up to answer