We have a project with several Scrum boards (one per squad) and are working towards a release. We're using "Story Points" for our estimation and are not tracking time in Jira (for several reasons). Most of the stories are correctly pointed and I can see the progress bar in the Releases tab.
I'd love to see a release burndown report to determine how well we're trending to our release. However, when I select that report and the release, I get a message saying:
There are no estimated issues in this version.
Things I've checked:
(I had accidentally asked this in the "Jira Mobile Apps" board previously)
Hi @Ian Epperson - The release burndown requires the completion of at least one sprint before the report will return anything. Have you completed your first sprint yet?
We have over 100 sprints complete across the different squads, but I realized that we didn't have any issues for this release in any completed sprint. I edited the last sprint to add in the "fix version" and now I see data on the Release Burndown!
Thank you so much!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Spend the day sharpening your skills in Atlassian Cloud Organization Admin or Jira Administration, then take the exam onsite. Already ready? Take one - or more - of 12 different certification exams while you’re in Anaheim at Team' 25.
Learn more
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.