Hi All,
I have been playing around with Portfolio v 2.0, I am facing few issues, are they bugs or is it the way JIRA portfolio has been designed? Along with Epic I am using "Feature issue Type" at the same level of hierarchy underneath the Initiative issueType.
Hi Tarun, to move an existing story to another epic, switch to the stories hiearchy view (hierarchy switcher at the right above the table), find the story there, and use the "Epic" column to set a new parent. if that column is not visible, you might have to display it with the column selector. > we're working on improvements to make this easier, but this is how you can reach it right now in 2.0
regarding hierarchy / issue links: the parent/child relation is not mapping to the concept of issue links by design, but is stored separately (similar to the epic-story link on agile boards). it currently does not show up on the issue, but also for this we're prototyping solutions, potentially as a field similar to the "Epic Link" on the issue.
Hope this helps! Best, Martin (PM for Portfolio @ Atlassian )
Thanks, I am now able to map orphan stories to new parents! Though from the UX point of view it would be really nice if drag and drop works for this feature.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.