Problem with remaining time shown on epic in structure/Jira vs BP

Scott Hassell February 12, 2025 edited

Hi,

Problem: We have an issue showing up on an epic. It is showing 1608hours remaining, but we believe should be showing 35 hours.

Background Info:

  • We use Jira, BigPicture(BP), and structure.
  • In BP if we use auto bottom up and have the field set to sum without parent, we get the 35 hours remaining but summing up the stories in the epic. If we chose sum, we’ll get 1608.
  • In structure when we have a column for remaining estimate we only see 1608.

 

Desired outcome:

  • Please advise what can we do such that it shows 35 hours remaining in structure/Jira field to match what we see in BP when we do sum without parenBigPicture -  Showing hours with sum without parent and with sum 1.JPG Epic showing incorrect remaining time 1.JPG Structure showing remaining estimate 1.JPG

1 answer

0 votes
Stepan Kholodov _Tempo_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 13, 2025

Hello @Scott Hassell 

If the value is missing both in your structure and in Jira, then it seems like a synchronization-related matter in BigPicture. Structure can only work with data/field values that are present in issues in Jira; it doesn't have access to the data stored inside other apps. So, if the data you need appears in issues and/or it can be referenced by JQL, only then Structure can work with it.

I hope this helps. If you need further assistance or have other questions about Structure, please reach out to us directly at our support portal.

Best regards,
Stepan
Tempo (the Structure app vendor)


Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
atlassian, team '25, conference, certifications, bootcamps, training experience, anaheim ca,

Want to make the most of Team ‘25?

Spend the day sharpening your skills in Atlassian Cloud Organization Admin or Jira Administration, then take the exam onsite. Already ready? Take one - or more - of 12 different certification exams while you’re in Anaheim at Team' 25.

Learn more
AUG Leaders

Upcoming Jira Events