Hi,

Problem: We have an issue showing up on an epic. It is showing 1608hours remaining, but we believe should be showing 35 hours.

Background Info:

  • We use Jira, BigPicture(BP), and structure.
  • In BP if we use auto bottom up and have the field set to sum without parent, we get the 35 hours remaining but summing up the stories in the epic. If we chose sum, we’ll get 1608.
  • In structure when we have a column for remaining estimate we only see 1608.

 

Desired outcome:

  • Please advise what can we do such that it shows 35 hours remaining in structure/Jira field to match what we see in BP when we do sum without parenBigPicture -  Showing hours with sum without parent and with sum 1.JPGEpic showing incorrect remaining time 1.JPGStructure showing remaining estimate 1.JPG