Portfolio for Jira sprints aligned with scrum board sprints?

Hi,

I have set up a plan in Portfolio for Jira. The issue source is a filter. The team assigned to the stories in the portfolio is connected through a scrum board. 

In the portfolio view, a sprint planning is automatically set up. Though, this sprint planning differs from the one I can see on the scrum board.

When I instead set the issue source as the scrum board the sprints are the same as on the scrum board.

How come the sprint planning differs when I use a filter instead of the board, when it contains the same issues and team?

Thanks in advance.

0 answers

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published yesterday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

58 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you