I would like to change the description of these fields, but I can find them under Field Configuration. Is it possible to change the descripcion of these fields?

Thank you.

1 answer

1 accepted

0 votes
Answer accepted
Monika Antos [Adaptavist]
Contributor
January 18, 2012

The 'Time Tracking' field adds a group of fields (Original Estimate, Remaining Estimate) which provide the ability to specify/modify time estimates. You can change the description (but not the name) for these: go to 'Field Configuration' > 'Time Tracking' > 'Edit'.

Note that these fields will not be available to add to any screen if Time Tracking is deactivated.