Number of days remaining in active sprint board is not displayed anymore

Alina Mitroi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 16, 2023

Number of days remaining in active sprint board was properly displayed until a few days ago. It was placed before ''Complete sprint'' tab. Today it looks like it disappeared. How can I add back this information?

image.png 

1 answer

1 accepted

3 votes
Answer accepted
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 16, 2023

Hi @Alina Mitroi ,

I am still seeing this in my instance. Do you have other sprints going on that you can check just to confirm that it is a systemwide problem?

My guess is that some change has rolled out into your instance, and not mine as yet, that has resulted in this disappearance. If that is true, either it was planned or or a regression was introduced. Either way it might be worth opening a support ticket with Atlassian.

Alina Mitroi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 16, 2023

Thank you! I managed to find out the root cause. It was because I had 2 sprints sunning on the same time. Thank you so much for your support!

Like # people like this
Mason W_ Foley October 30, 2024

In spite of that though, they should still show when the sprint is filtered to one.  Usually a refresh allows for it to show up.  Feels like a bug with JIRA that it doesn't show all the time and requires "voodoo" to get it to show up.