Hi,
I am planning to migrate my existing team-managed projects to company-managed projects. I have read some instructions online and seen videos on YouTube about things to note during migration. I understand the process well.
However, I do not understand the EPIC Name field during migration. The steps online suggest that the way EPICs are linked is different in company-managed projects.
It doesn't seem to be a mandatory field for me and I have selected the retain check-boxes in the migration steps. The EPIC Name field also doesn't seem to exist in my company-managed project. The EPIC I have migrated seems to have retained everything correctly.
So my question is, am I missing anything here or is this based on some individual Jira settings?
Additionally, are there any key points I need to note before performing the migration in a way that ensures all the links and issues of my team-managed projects are retained correctly?
Thanks!
Hi @Amulya Sankara ,
It sounds like this Question might be more related to Jira vs. Jira Product Discovery. You have opened this within the JPD Community - so do want to ensure we are providing the best possible answers.
I would also like to note that if this is related to JPD - JPD only offers team-managed projects at this time. Let us know whenever you have the chance. We can always transfer this to the correct product if needed.
Hi @Nick Haller
Apologies. I meant to add this question for Jira, not Jira Product Discovery. It would be great if you could move it to the correct product. Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.