Hello Community,
I need your recommandation on how to do an audit for cloud migration for Data Center Jira.
Best Regards,
I would suggest using this guide. https://www.atlassian.com/migration/plan/cloud-guide#atlassian-team
It is important to run a few test migrations to develop check lists like:
Many of the items you will want to check can be done through the API - https://developer.atlassian.com/cloud/jira/software/rest/intro/
Once you have that in place you will need to construct a formal user acceptance testing checklist of items that you would like Admins, users, etc. to check.
Then run the migration once you have all of this in place. The amount of work depends on the instance size.
Hello @Seifallah Bellassoued
Can you provide more information about what you mean by an audit?
Are you trying to prepare to migrate from DC to Cloud? If so, have you checked the resources that Atlassian provides?
https://www.atlassian.com/migration/plan/cloud-guide#introduction
https://support.atlassian.com/migration/resources/
Are you trying to review a migration that has already been completed?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.