JIRA 4.4 activity stream showing old JIRA url

Arthur Maltson August 9, 2011

Hello everyone,

We're starting to upgrade JIRA at my work place and I've been going through a test run on a test server. The upgrade has gone smoothly but I've run into an issue with the Activity Stream widget showing links to the existing production JIRA instead of links to the test server. Other widgets like "Assigned To Me" and "Issues in progress" point to the test server.

Any help would be greatly appreciated, thank you.

2 answers

1 accepted

2 votes
Answer accepted
Giacomo Zucchelli August 9, 2011

Hello,

have you changed the "BASE URL" in the general configuration? that one must point at the new server.

Arthur Maltson August 9, 2011

Perfect! Works great, thanks.

0 votes
Veenu Bharara
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 10, 2011

Yes BaseURL is the culprit here. The new functionality like activity stream, Applinks use the base URL defined in JIRA. Update the baseURL of test server in "General Configuration" page and the issue should be resolved.