Accidentally started a sprint (on the Rapid Board) and it's been running a while before we realised that it's end data was July, not June. (Hadn't noticed the date picker had moved forward a month).
Is there a way to change this date with the sprint running so that all the burndown charts etc show proper graphs? I cannot find an option for this.
Sure. In plan mode expand the Sprint summary box at the top of the backlog then click the dates to edit them.
Thanks,
Shaun
Thanks, that was it. I was certain I'd looked there. Guess I was wrong.