Hello everyone,
I hav a question, that caused me some gray hair so far: Is it possible to report only status changes in a defined Period? How do i do that?
Here is my query: "project = Projectname AND updated >= -1d" That gives me all changes on issues made in the last 24 hours. So far so good. But I on ly want to see the issues where the status value changed in the last 24 hours. How do I do that??
Ich hope someone can help me out of this...
Thanks a lot in advance,
Martin
Hello Martin,
I don't know of an inbuilt JQL option.
Maybe the "HP/Palm Jira Search Plugin" helps? See this picture: Instead of "Issue Type" "changed" "in relative range" you might be able to use "Status" "changed" "in relative range".
I did not test this on my test installation; answer just from watching the plugin-webpage
BR, Markus