When i create a subtasks for a parent tasks, i want to link the closure of the sub tasks to the main task ( meaning unless all the subtasks are resolved, the parent task cannot be resolved.) How do i create such a dependency
Hi Kantamneni Nrupen,
You can use the Sub-task Blocking Condition as Krister Broman already suggests.
In case you want to display an error message to warning your users why parent issue cannot be transitioned yet, install Workflow Magic Box (FREE) and use their SubTasks Status Validator
See the following documentation page, for further information.
Tell us if the above proposal solves your problem,
Regards
Hi!
I am Antonio from atSistemas. I am the lead developer of this app. Please let us know if you have any problem configuring or using it. You can contact us using our Helpdesk.
Best,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Use a condition in the parent workflow. See this guide
https://confluence.atlassian.com/adminjiracloud/configuring-sub-tasks-818578898.html
How to block a parent issue workflow based on a sub-task status