Given:
As-Is:
Question:
How to set up the Plan so that only estimates from epics are considered in the Projected sprints?
Hi @Igor Koltun and welcome to the Community!
To be honest, I don't think this is going to work. Epics are not planned in sprints (from a scrum board, Epics appear on the epics panel in the backlog and can't even be added to a sprint), and it is even a common scenario that work on an epic spans multiple sprints.
It may be interesting to read up on the following documentation to learn how Plans deal with capacity:
Hope this helps!