Future Sprint Field Removed from Issue when Auto-Managing Sprints

Scott Derderian
Contributor
January 20, 2025

We have upgraded to JIRA 9.12 relatively recently, so auto management of sprints is relatively new functionality to us.

I had a user today indicate that they had some issues that were assigned to future sprints, that had the sprint value removed during the sprint transition, thereby placing the issues in the backlog.

Has anyone else experienced this?   And if so, what guidance can I give my users as to what to watch out for so that this does not occur in the future.

Thanks in advance!

1 answer

0 votes
Layssa Souza
Contributor
January 21, 2025

Natively, the sprint change happened as shown in the print below.
Evidencia - Sprint.png
Is this behavior different for you? Would there be evidence of how the user performed the action?

 

 

CJ Jang
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 21, 2025

Hi, I'm the user. @Layssa Souza . Rather than manually completing the sprint like in your screenshot, I checked the box for "Start and complete sprint automatically" as in the screenshot below. For the sprint that completed automatically, it worked correctly, moving open issues to the backlog. However, it ALSO moved some issues out of future sprints (that had not started or completed yet) into the backlog as well, which was not expected.  Screenshot 2025-01-21 at 12.39.33 PM.png

Like Layssa Souza likes this
Layssa Souza
Contributor
January 21, 2025

@CJ Jang 

 

I understand, I did some simulations in my environment, but I couldn't reproduce the same scenario.

Could you share 2 problems that experienced this scenario? And 1 problem that went through the change correctly?

Here it would be interesting to have the history of changes to questions, to be able to map possible problems.

1 issue that was in the sprint and was correctly moved to the backlog – issue history

2 issues that were in future sprints and were incorrectly moved to the backlog.

 

Thanks.

 

CJ Jang
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 22, 2025

@Layssa Souza Sprint DCP 2024Q4.5 completed on January 20th at 10am and open items from that sprint moved to the backlog as expected. However, nothing displays in the History where it worked correctly, as they are still part of the DCP 2024Q4.5 completed sprint. Below are examples in the history where items were moved out of future sprints.

 

incorrectly moved from sprint 1.pngincorrectly moved from sprint 2.pngFuture sprints.png

Layssa Souza
Contributor
January 23, 2025

Hello, @CJ Jang 

I carried out some more tests here, and I noticed that when it is removed from the sprint, no action is generated in the history.
I was able to observe that the execution of the anonymous user may have something to do with external automation. That said, is there any automation aimed at sprints? Is it removing issues from the sprint that are linked, or that have some component that causes issues to be considered as peers?

Furthermore, the version I was able to perform the tests on is version 10.3.2, which could even be a version bug. It might be interesting to open an issue with Atlassian support for evaluation.

 

Best regards.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
SERVER
VERSION
9.12.13
TAGS
AUG Leaders

Atlassian Community Events