Does JIRA calculate velocity for TASKS (not Subtask)

Gyanendra Agrawal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 5, 2025

 

In Our Scrum Board we are not using Stories. We are using Tasks (Not sub-task).

We estimate TASKs in story points. Will JIRA show the velocity chart?

1 answer

0 votes
Arnelys March 5, 2025

Yes, but you have to have more than one closed sprint because the velocity of a sprint is calculated by averaging the total estimates completed in the last sprints

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, team '25, conference, certifications, bootcamps, training experience, anaheim ca,

Want to make the most of Team ‘25?

Spend the day sharpening your skills in Atlassian Cloud Organization Admin or Jira Administration, then take the exam onsite. Already ready? Take one - or more - of 12 different certification exams while you’re in Anaheim at Team' 25.

Learn more
AUG Leaders

Upcoming Jira Events