Custom CANCELLED status issues don't complete with sprint completion

Teodor Grancharov
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 19, 2024

I added a custom status called `CANCELLED` in `DONE` Category:

Screenshot_90.jpg

 

The stories switched to that status get a strike through as done in the current sprint, but when I close the sprint they re-appear in the next started sprint:

Screenshot_91.jpg

How can those be considered `DONE` even if with custom `CANCELLED` status and not re-appear again.

1 answer

2 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 19, 2024

Hello @Teodor Grancharov 

Welcome to the Atlassian community.

For sprints an issue is considered "complete" only if it is the column farthest to the right on your board. The actual status doesn't matter, as long as it is in the right-most column.

You can have multiple "done" statuses, but you will have to map them all to the right-most column.