I am faced with a challenge that was asked of me, which is the following: When faced with an impediment, the development team must add a Flag to the issue. But, when the Flag is added, 5 fields must be filled in, which could be through a pop up after placing the Flag. Can you tell me how I would do this using Scriptrunner or Automation Rules?
Emanuel Lima
Thank you
BR
There are several options and it will depend on your current configuration and how you´d like to handle the situation, for instance:
You can have a Workflow Status called Flag, and when you transition from any other status to it, you´ll be requested the 5 fields which would be required in the workflow transition.
Let me know if it works for you or if you have another thing in mind regarding your initial configuration.