Burndown chart is not burning down

Ievgenii Kompaniiets March 24, 2020

I created a board to track my sprint where I want to see burned stories when they are not fully done.

I put several statuses into the most right column:

Screenshot 2020-03-24 at 09.25.17.png

My active sprint board looks like this (I have many stories in Done column):

Screenshot 2020-03-24 at 09.27.58.png

 

But my burndown chart doesn't burn anything:

Screenshot 2020-03-24 at 09.32.48.png

How I can make it burning my stories? 

2 answers

1 accepted

1 vote
Answer accepted
Ievgenii Kompaniiets March 24, 2020

I found a reason for this behaviour: my completed stories where completed outside of the sprint. It was clear from the sprint report. 

0 votes
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 24, 2020

Hi @Ievgenii Kompaniiets , the status mappings look rather untraditional in that you have In progress category statuses in the Done (right most) column. That said, have you verified that all of your issues in the done column have proper time logging. Also, make sure your truely Done (green) issues have the Resolution set.

Ievgenii Kompaniiets March 24, 2020

I'm using Story Points estimation. What do u mean by proper time logging?  U can see from the screenshot that I have two stories with 3 and 5 story points in my Done column. I want to see 8 story points burned down on my report.  

Ievgenii Kompaniiets March 24, 2020

We have a following schema: Done means story is deployed to production and verified on production. 

Most often we deploy to production on the last day of the sprint or even in the beginning of the next sprint. 

Burn down report is just unusable to me if I use Done status only.

But I would like to see the progress when story is verified on test environment (it is still not done). 

If this is unusual, could u please provide me a tip how to reorganise this to use reporting?

Documentation is telling that report consider last column as criteria of Done. It looks great to me, but in fact doesn't work. 

 

Done 

Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 24, 2020

I was assuming you were using time based logging.

What are the statuses of MB-96 and 97? 

TBH, I have never used an in progress status in the right most so unsure of the behavior that will result. It is reasonable to assume it should burn down but I’m just not sure. Now if 96 and/or 97 are in a Done category that nullifies any theories around an in progress status being the smoking gun.

Ievgenii Kompaniiets March 24, 2020

Both are "Merged to DEV"Screenshot 2020-03-24 at 14.48.23.png