Hi, I have Epic 1 , Epic 2 , Under Epic 1 - I have story A and Story B and Under Epic 2 Story C and Story D - Under the story we have sub tasks,so based on the Sub Task transition, let say Sub Task of Story A moved from OPen to Inprogress Automatically the story A & Epic 1 has to move to IN progress and which should not impact the Story B,C or Epic 2 - Automation Rule for this is needed, If anything is there, please suggest
Hi @Naveenkumar You can create 2 separate automation rules.
1st when the sub-task transitioned to status Done then transition the story to Done
2nd When the story transitioned to status Done, then the Epic to Done. (Note: check the box to run this rule in response to other rules).