Issue with carry over story with sub-task charging and its burn down chart

Edited

Hi,

we are facing issue with incomplete user stories, we need to carry over these stories and user already charges for their sub-tasks. If we carry over these stories to next sprint, the already charged hours are also carry forwarded to new sprint. this makes wrong calculation in burn down chart of new sprint.

I hope, I'm clear with my question.

or please let me know in case of more details required.

Please help to resolve this issue.

 

1 comment

This is not a "wrong calculation".  You did not complete the story you said you would do, so it carries over into the next sprint with its full estimate.