Issue with carry over story with sub-task charging and its burn down chart

Abhishek Pethia September 11, 2019

Hi,

we are facing issue with incomplete user stories, we need to carry over these stories and user already charges for their sub-tasks. If we carry over these stories to next sprint, the already charged hours are also carry forwarded to new sprint. this makes wrong calculation in burn down chart of new sprint.

I hope, I'm clear with my question.

or please let me know in case of more details required.

Please help to resolve this issue.

 

1 comment

Comment

Log in or Sign up to comment
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 15, 2019

This is not a "wrong calculation".  You did not complete the story you said you would do, so it carries over into the next sprint with its full estimate.