The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Creating Sprint from WBS Gantt Chart

Goff
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 15, 2019

Hi,

I have over 1000 issues and tasks in my WBS Gantt chart, which I suppose form my issues backlog. When I drag and drop the set of issues into the respective sprints I created, the issues are no longer in the Gantt chart. What am I doing wrong? Shouldn't I be able to keep my Gantt chart intact along with my sprints? Thanks.

Goff

2 comments

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Admin
May 27, 2020

I am also facing the same issue. Is there any solution for this???

Parker Cain
June 16, 2020

are you using  a filter that includes the sprints? I have a gantt that sounds similar to you. if you want to have a gantt that shows what is in the sprint you could use a filter:

sprint = 1234

or if you want all open and future sprints you could use:

Sprint in (openSprints()) OR Sprint in futureSprints()