When team members are working on multiple projects, stories and tickets, it is important to track how long a workflow took from start to finish. This will help project managers, team leads and other stakeholders to get a better understanding of how long specific workflows take, to spot variations in efficiency, check if processes should be optimized and if teams need more resources.
Our Report Builder “Lead Time” report is extremely useful to teams, as it indicates how long it takes for work to flow through the pipeline. The report measures the total time elapsed from the creation of work items until their completion. The lower the lead, the faster the throughput of your team.
The following diagram illustrates how Lead Time relates to Jira Scrum or Kanban ticket workflows. The Lead Time is calculated from work item creation to entering the completed state.
Summary elements:
Interactive elements:
Test Report Builder 30 days for free and discover your possibilities. Already available on the Marketplace
Andrei Pisklenov _Actonic_
Head of Development
Actonic
Germany
3 accepted answers
2 comments