am trying to mention in the road map the percentage completed of all tasks for a project . s what will be the process ?
I think it depends on what you mean by percentage completed. If this is just open vs. closed tasks, you should be able to get that e.g. via the Issue Statistics or the Projects dashboard gadget.
If you need a more sophisticated calculation (e.g. based on sub-tasks etc.), you may need one of the many reporting apps from the Atlassian Marketplace. I know that EasyBI is very popular; maybe someone from the team can jump in. You can also get this value with one click in the app that my team is working on, JXL for Jira:
(You can calculate the progress using a lot of different methods; the above is just the default view.)
Hope this helps,
Best,
Hannes
It is possible to retrieve the completion progress % for a project via eazyBI. The first thing is to define what you consider completed work and what you include in the total work scope.
You might look at some samples for inspiration here - Sample reports .
Please feel free to try by yourself or ask for assistance if needed.
Regards,
Oskars / support@eazyBI.com
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
👋 Hi there Jira Community! A few months ago we shared with you plans around renaming epics in your company-managed projects. As part of these changes, we highlighted upcoming changes to epics on...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.