Help create another rule.
If the release date has changed, the due date in the tasks of this release should also change.
release date = due date
hello @Zylot_x
Thank you for reaching out. Sorry for not answering your question previously, I didn't receive a notification about your last reply.
Per your description, I understand you want the following:
If that's what you want, you can configure the automation rule below. P.S: update the JQL parameter "project = scrum" with the project you have:
Let us know if this works for you.
@Petter Gonçalves Can you give me the exact format to set the Fix version's release date to issues release date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you give me the exact format to set the Fix version's release date to issues release date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.