At the top of the control chart are some metrics. An example of that would be:
3w 5d 18h average 22h 58 mmedian 0 min time 25w 5d 20h max time 30 issues
1) What exactly are the Average, Median, Min Time and Max Time tracking?
If the average is 3w 5d 18h, what exactly does that mean. Is that 3x40 hours (3w) + 5x40 hours (5d) + 18 hours?
2) Are these numbers "effort"? or are they "elapsed time"?
3) If the answer is "effort", why is the report not using the "issues -> time tracking" settings?
Our settings are 5 days a week, 8 hours per day. Based upon what I see, I think the answer is NO.
Thanks in advance for shedding some light on this subject. I read the documentation, but there was no mention about these numbers.
Yes, it would be great if someone could answer the question regarding the meaning of these values.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.