Zero remaining hours on subtask not using time.

Mike Ballinger May 14, 2021

I have automation rule that zeros's remaining hours when subtask is transitioned to done.

If user has NOT entered any hours i.e. enabled time tracking for a particular subtask the automation fails.

Is there a way to detect that a field exists?

1 answer

0 votes
Fazila Ashraf
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 16, 2021

Hi @Mike Ballinger 

Can you share the screenshot of the automation that you have set?

I do not think the automation should actually fail if the value is null.

For you question: Is there a way to detect that a field exists? -> you could add another condition to check whether the field has some entries already. 

Mike Ballinger May 17, 2021

my bad - looks like time tracking was dropped on the sub task in question after the automation had been implemented. 

Fazila Ashraf
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 17, 2021

@Mike Ballinger  , So it is all good now? :) 

Suggest an answer