Parent task's status (percent complete) calculated by its sub-tasks' status/completion?

Chris Chambers
Contributor
March 22, 2018

It's been a while since I posted this question.... help? please?  :-( 

--------------------------------------

I'm sure this has been asked before, but I've had no luck finding a solution that matches my case...

Using Jira Service Desk only (I don't have Software) - a customer creates a request for a new system implementation.  Upon approval a post function creates 10-20 subtasks and assigns them to a member of a team to work on.

Since subtasks can't be seen by the customer (no Request Type attributable to the subtasks), but the parent task can, how do I update status, showing percentage complete, of the parent issue as team members complete the subtasks?

I don't, necessarily, need time tracking per subtask adding up to equal the parent's overall time estimate -but something as simple as "if this subtask is complete, subtask 1 of 10, show the parent as 10% complete."  Then, with each subtask's subsequent completion, "add" another 10%/ea to the parent's completion percentage.

Assuming there will be several of these requests in-flight at once, is there a way to provide a report to the customer showing all their issues (parents) with each issue's individual percentage complete?  And what break-downs might be available to the customer, as the subtasks won't be visible?

 

Thank you!

1 answer

1 accepted

1 vote
Answer accepted
codeatsg
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 13, 2018

Hi Chris,

Thanks so much for your question. Currently, we don't support this functionality.

We're always working hard to improve Jira Service Desk for every user, by balancing the short and long term needs of our customer base.

If you feel like this is something we must address, please raise a request with Support <https://getsupport.atlassian.com>.

Thank you,
Jira Service Desk

Chris Chambers
Contributor
September 14, 2018

Thank you.  I was able to do something similar, with help from the forums, calculating the percent of the parent task complete based on its number of sub-tasks which are complete.

This gets me where I need to be, so the percentage complete based on percent of each sub-task's completion is a nice-to-have at this point, but not a need-to-have.

 

Thanks again,

Chris

Stan Olbrot September 17, 2018

Can you explaine more ?

I'm working on exectly same problem.

Chris Chambers
Contributor
September 17, 2018

I used a calculated custom field (using SIL script) to count the number of the parent item's sub-tasks, then count the number of those that were in "Done" status.

Percent was calc'd:  (DoneSubTasks / TotalSubTasks) * 100)

Actually, the formatting of the returned value removed the need for the * 100.

Details are in the question I asked here: 

https://community.atlassian.com/t5/Jira-questions/Calculated-Field-using-SIL-script-how-to-filter-subtasks/qaq-p/890451#U890490

Scott Barnard June 5, 2019

Where do you run SIL scripts against Jira if not an Admin?

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events