Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Configuration of tasks with no SLA and subtasks of this tasks with SLA

Sebastian_Kalata
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 20, 2020

I need to create the following configuration - projects and tasks with no SLA, but I need sub-tasks (in two types) with SLA. How can you achieve this effect?

1 answer

0 votes
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 20, 2020

you should be able to accomplish this simply by defining the Goals of your SLA and incorporating "issuetype = subtask".

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events