You can generate the report by going to the Project, clicking on Reports on the right.  In the window scroll down to User Workload Report under Forecast & management.

Hopefully that helps!

Cheers,

Branden

Thanks Branden.

This option gives me to generate only for the particular project, but i required to generate the User's Activity report for all the user's across the projects with monthwise.

 

Did you manage to find such function/report ? I am also looking for such an option

As am I. We need to produce a monthly report of all JIRA users for auditing purposes.

Anyone figure out a way to do this Jira-wide, not just for one project?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted in Jira Service Desk

Tell us how you've implemented Change Management

Hello Community 👋, I'm a product manager at Atlassian, looking at improving change management capabilities across our products. In particular, we're looking at bridging the gap between Dev & ...

546 views 1 10
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you