Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Custom field to calculate dates

Hey,

In order to use the Timeline view in a way that makes sense to my team, I would like to create custom fields that calculate the dates based on Formula. Particularly I need:

1. Start date - I have a custom numeric field called "work starts on sprint", I want that number to be translated into a date, based on a predefined list of sprint start dates.
in case this is completely undoable, then I will just have it as a regular date field, but this would be more better for me.

2. Guesstimated Delivery date - I would like to use a combination of the Start Date + amount of weeks based on Effort field with either t-shirt size or 1-5 scale, e.g. Start date March 1st, Effort M (pre-defined as 4 weeks) = Delivery Date March 28th.


I would really appreciate any help with this.

2 comments

Comment

Log in or Sign up to comment

Along those lines, I would like to customized the timeline, as we dont work on standard quarters, our planning sessions are not consistently three months.

Hermance NDounga
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Feb 15, 2023

Hi Ronnie, 

Thanks for your feedback. At the moment, these aren't possible with the timeline view, but as it is still recent, we continue on improving it.

Based on your comment it seems that you are doing some manual work to have your sprint dates and estimation into Jira Product Discovery. 

Do you already have your sprint dates, T-shirt sized effort and estimated releases date already in Jira Software at the moment and copying these information in Jira Product Discovery? 