Start(ed) sprint vs aka future sprints, how it all works

Hi,

Looks like I can start Sprint no matter what start/end dates are, in this case what all call "Future" sprint? is only base on date range ??

I also see that once Sprint started (have those 3 status color cirles) then you can not delete it, even if no issues are assigned to it.

I appreciate if anybody can help me with those definitions.

 

Tx

Mario

1 answer

This widget could not be displayed.

Hi Mario,

According to JIRA terminology a future sprint is a sprint which is being planned but has not been started. Also you can delete only planned sprints(sprints that are not yet started).

Regards,

Peter

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted yesterday in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

45 views 2 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you