Getting error : jira align sprints not in calendar order
not sure though what is the issue. dates and mapping look to be okay.
see attachment.
@manish a This is just occurring because based on the sprint ID numerical order (oldest to newest), the system would expect the dates to be flip flopped (oldest to newest). So on Sprint ID 3026, it is expecting the dates would have been 8/17-8/25 and Sprint ID 3028 would have been 8/28-9/8. If your sprints are mapping to the correct anchor sprint (far right), then you can just ignore the error.