You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
Which is the appropriate report in Jira Align to know when a Feature (Jira Epic) would be completed for the following scenarios:
1. A Feature (Jira Epic) has Stories from a team only
2. A Feature (Jira Epic) has Stories from multiple teams; pls. suggest.
@Vinay Sharma, I would recommend using the Program Board, though others out there may prefer another visualizations or reports. If you navigate to the Program Board, you can see when functionality will be delivered at various points of the upcoming or current time period.
1. A Jira Epic, with stories from a single team, will appear in the designated team swimlane and will appear in the sprint column when the last story is scheduled to be completed.
2. A Jira Epic, with stories shared by multiple teams, will appear in multiple swimlanes. The respective rectangle (Jira Epic) will appear in the sprint column when the last of that team's story commitments will be completed.
Based on the screenshot below, you can see this Jira Epic is a shared commitment between Team Baltimore and Team Cowboys. They are both forecasting to complete their stories in S27. Unfortunately, the Jira Epic is blocked (red rectangle) because of a blocked dependency on Cowboys (red chevron).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.