Caveat: I'm relatively new to JIRA Align, am self-taught and am responsible for implementing JIRA Align for our existing teams. We currently have about a dozen ARTs and approximately 90 teams within our organization.
I'm looking to understand the sequences / best practices for adding a new team to existing ARTS (even during a PI...which is my current situation). Specifically, what is the suggested guidance for setting up the Anchor Sprints (sync'd with the rest of the ART) for this new team after things (i.e. Sprints) have already been established for the PI.
I'm familiar with the general sequence as described here (https://help.jiraalign.com/hc/en-us/articles/115005897808-Create-agile-teams) but this doesn't get into the specifics of establishing the Anchor Sprints etc.
Thanks in advance for the help!
If each team does not have it's own Jira Project; the Program Jira Project is already integrated to JA and you have already parented the Team (based upon their board, which is done in Jira Management --> Add Board) (see screenshot), then the team will already be part of the Program.
Once the team creates their actual Sprints to match the remaining Sprints in the PI and the Board is synced the sprints from their board (with appropriate dates) will appear in the Jira Sprints with their mapping to the JA Sprint
Screenshots:
Thank you Steve, for such a detailed / thorough answer!
I'm still on the steep part of the learning curve with this tool and you've helped me a ton!