Program Boards in Jira Align

Lucy Chien_ Chialing
Contributor
July 17, 2024

 

we have Program Boards in Jira Align. They serve as a kind of dashboard. But I don't know how to get to the data behind the dashboard. I'd like to baseline program boards by ART.

 

Link to board. 

 

Jira Align

2 answers

1 accepted

2 votes
Answer accepted
Kit Friend
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 17, 2024

Your data isn't accessible (thankfully :) ) to us here on the forum - based on the URL I assume you're talking about this style view though:
images (1).jpeg

 

The data driving this in terms of sprint allocation etc is all in the item details if you click on them, could you clarify/provide a sketch of what you're hoping a baselined view by ART would look like - is it a big table with the original vs current iteration allocation of each feature? I'm not sure if historic iteration allocation at a point in time is recorded in a way you could expose easily if so (and the table would get massive)...

0 votes
shiva kumar Gosul
Contributor
August 30, 2024

You can take a snapshot by clicking "Capture" top right