Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

On the Roadmap how is the percentage complete calculated for Epics/Features?

Edited

When using the Jira Align Roadmap view Features by Epic, how are the completion percentages for each calculated? I can't seem to locate these calculations in the support information.

Thanks - Greg

1 answer

1 accepted

2 votes
Answer accepted
Mark Cruth
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jun 18, 2020

Great question! The % visible on the Epic and Feature bars on the roadmap is calculated by dividing the total accepted effort (story) points from all the child stories by the total effort points planned from all the child stories.

Ex. If I have 100 points planned across all the stories associated with a Feature and have accepted 50 of those points, the Feature bar would show 50%. 

Hope that helps!

Thank Mark for the quick reply. 

@Mark Cruth hi Mark, what about when the stories are estimated by hours, considering that some stories will take longer than estimated in hours?

Mark Cruth
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Mar 26, 2021

Hi @Margarita Artemyan ! In Jira Align, the concept of story / effort points is what will ultimately drive the progress bar on the roadmap (tied to the LOE field on stories). Points act as a proxy for time / complexity. I'd recommend checking out this article to learn more: 

https://www.atlassian.com/agile/project-management/estimation

Hope this helps!

Mark