Is it possible to define all sprints for an ART in one place? or must this be done team by team?

Bob Hunt
Contributor
July 18, 2024

I know we have a mechanism to create sprints for each team individually but I'm wondering if there is a way to create these for the entire ART or (ideally) for an entire portfolio?

2 answers

1 accepted

0 votes
Answer accepted
Nicolas Grossi
Banned
July 18, 2024

@Bob Hunt By team, Sprints are per project

 

Nicolas

Bob Hunt
Contributor
July 18, 2024

Thank you! I was hoping that this could somehow be centralized to reduce the creating burden and the ensure that dates etc. are easily aligned across the teams.

 

0 votes
Rae Gibbs
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 19, 2024

Are you asking for Jira or Jira Align?