You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
If an ART requires different start and end dates for a PI (in comparison to other ARTs in the portfolio), would it require to create new portfolio to accommodate it: pls. suggest
ARTs can have different start and end dates within the same portfolio. There's no need to create a new portfolio to accommodate that one ART.
The only thing you'll need to make sure people are aware of is when they want to look at views for the entire Portfolio (for example, looking at the Roadmap view), they'll need to include the PIs for all the different ARTs within the Portfolio. So if your Portfolio has two separate PI schedules, you'll want to make sure you include the two different PIs in the Tier 1 filter.