I have below sprint cadence for a PI and I want to know what is the best way to generate sprints in Jira align. As sprint duration for 2021.PI6.S4 is 5week days.
I was thinking to mass add for S1-S3 with PI start date: Nov24, 2021 End Date: Jan4, 2022 and then single add for S4. ? But, my question is can I change PI end date to Jan11, 2022 after I generate sprints for S4?
2021.PI6.PORTFOLIO
2021.PI6.S1 ( Nov 24-Dec 7)
2021.PI6.S2 (Dec 8-Dec 21)
2021.PI6.S3 (Dec 22- Jan 4)
2021.PI6.S4 (Jan 5-Jan 11)
Thanks,
Sachin.
Absolutely! You can and should!
Hello Sachin,
You can and should absolutely update the PI start / end date to match the dates you set up the Anchor Sprints / Iterations.
Sincerely,
Samit Mehta, 321 Gang