How to generate sprints in jira align for sprints with different cadence?

sachin gangam
Contributor
November 5, 2021

Hello All,

Happy Friday!

I have below sprint cadence for a PI and I want to know what is the best way to generate sprints in Jira align. As sprint duration for 2021.PI6.S4 is 5week days.

I was thinking to mass add for S1-S3 with PI start date: Nov24, 2021 End Date: Jan4, 2022 and then single add for S4. ? But, my question is can I change PI end date to Jan11, 2022 after I generate sprints for S4?

 

2021.PI6.PORTFOLIO

2021.PI6.S1 ( Nov 24-Dec 7)
2021.PI6.S2 (Dec 8-Dec 21)
2021.PI6.S3 (Dec 22- Jan 4)
2021.PI6.S4 (Jan 5-Jan 11)


Thanks,
Sachin.

2 answers

2 accepted

1 vote
Answer accepted
Tina Behers
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 5, 2021

Absolutely! You can and should!

1 vote
Answer accepted
Samit Mehta _321 Gang_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 5, 2021

Hello Sachin,

You can and should absolutely update the PI start / end date to match the dates you set up the Anchor Sprints / Iterations.

Sincerely,

Samit Mehta, 321 Gang