Hello All,
Happy Friday!
I have below sprint cadence for a PI and I want to know what is the best way to generate sprints in Jira align. As sprint duration for 2021.PI6.S4 is 5week days.
I was thinking to mass add for S1-S3 with PI start date: Nov24, 2021 End Date: Jan4, 2022 and then single add for S4. ? But, my question is can I change PI end date to Jan11, 2022 after I generate sprints for S4?
2021.PI6.PORTFOLIO
2021.PI6.S1 ( Nov 24-Dec 7)
2021.PI6.S2 (Dec 8-Dec 21)
2021.PI6.S3 (Dec 22- Jan 4)
2021.PI6.S4 (Jan 5-Jan 11)
Thanks,
Sachin.
Hello Sachin,
You can and should absolutely update the PI start / end date to match the dates you set up the Anchor Sprints / Iterations.
Sincerely,
Samit Mehta, 321 Gang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The roadmap challenge for large scale agile enterprises Regardless of the agile framework you use, the agile enterprise has a massive scale with the challenge to connect hundreds of teams and thous...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.