Global Rank generally refers to the ranking of work items without regard for Program Increment. Check this page for details: Prioritize/Rank Work Items in the Backlog
Thanks Allan, I reviewed it before posting my question .
I was looking for additional insight on the following statement:
On a different note:
There is a button available "Prioritize" in the backlog view for Super admin but not for others roles. How do we enable it for other roles.?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Following - No answer from February 28, 2022 post - Thx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Global Rank is essentially the ranking of the Features when you have no Planning Interval/Program Increment/Quarter selected.
The Prioritize button is only available when at least one Planning Interval is selected because Prioritization with WSJF is per PI.
I believe the Prioritization button is available to all roles if the requirement of having at least one PI selected is met. Please let me know if you find this to be false.