Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Automatic capacity monitoring for features

Is there a feature in Jira Align where I can set the capacity of teams and as I load  epics for those teams it shows remaining capacity so that I dont have to manually keep track of how many points I have planned for Features and how many more to plan

 

1 answer

Hi Praveen,

If you are looking to understand your PI capacity and how much you are loading into the PI based on the Jira Epics/Features added to the PI from the backlog, this is possible from the Program Backlog.  You should be able to view the estimated program load in the header bar for the particular PI. 

If you know for a particular PI your team of teams capacity will be greater or less than normal, click on the gear icon next to "Override Program PI Velocity".  As you add Jira Epics/Features to the PI, the number next to "Jira Epic Estimate" will increase.

Screenshot 2023-02-15 at 8.20.11 AM.png

Alternatively, you can use the Kanban>Column View in the backlog to see a bar that shows the % load of the Program PI Load:

Screenshot 2023-02-15 at 8.23.43 AM.png

Hope this helps!

Cheers

Jean Henson

Director, Business Agility @ Aligned Agility, an Adaptavist Group Company

Thank you @Jean Henson , have you looked into the tool or found a way to capacity plan for horizon planning beyond the PI? I know the forecast tab has some of this functionality, but wondering if there are other options within Align to support longer term horizon planning for teams assigned to Epics and based on allocation the expected target completion date for accomplishing the full estimate/scope of the Epic given the teams historical capacity in points and % allocation for future periods. 

Hi @Anthony Smidl , Jira Align does have the ability to Forecast member weeks for future PIs (you must select more than the current PI in the Tier 1/Configuration filter) and to plan capacity. This can be accomplished via Program>Manage>Forecast, provided it has been toggled on in Roles.  Some information about the Forecast module can be viewed here:
https://help.jiraalign.com/hc/en-us/articles/115000592373

and here:

https://help.jiraalign.com/hc/en-us/articles/115000593093-Plan-capacity-for-forecasting

Cheers!