After adding a patch to an iterative pre-commit review, how do I mark a reviewer's status as "incomplete"?

Perry Hooker June 1, 2016

This question is in reference to Atlassian Documentation: Iterative reviews

After adding a patch to an iterative pre-commit review, how do I mark a reviewer's status as "incomplete"?

Uploading a patch adds content, but reviewers who have already marked the review "Complete" aren't notified.

1 answer

1 accepted

1 vote
Answer accepted
aborowski
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 19, 2016

In 4.0 we fixed https://jira.atlassian.com/browse/CRUC-6283 which seems to solve your problem.

If you are using Crucible 4.0 and latter and there are still some issues with uncompleting reviewers after applying patches, please contact Atlassian Support

Regards,

Adam