Documenting Projects in Confluence

mybucket2018 June 14, 2017

Within our organisation we could be running 65 projects or more at one time. Each project should contain their own decision logs, sprints, meeting notes, project scope, action logs, support document, etc...

Is it best to create a space for each project or is it better to list every project into a single space?

If we are to list every project into a single space I can see this quickly getting out of hand if our teams want to start giving their documents the same title. I can also see decision logs and meeting notes conflicting with each other. At the same time if we are to create a space for each project, this will overload our system with more spaces.

What do you think is the best solution?

3 comments

Robert Reiner _smartics_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 14, 2017

I'd recommend a space per project.

The number of pages will be the same, so we are only talking about the number of first level entry points to the wiki. You can label spaces to organize them and you could add additional pages as entry points for different audiences.

Spaces are handy if you for instance need to archive them, limit searches, or add access rights.

Like Sumesh Sukumaran likes this
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 14, 2017

I agree with Robert, a space per project is most manageable.  Your users will understand it, as the concept is intuitive and enables them to think and see things in terms of "this project".  They're natural containers for projects in most cases.

I would not wory about having too many spaces.  Confluence handles it fine, as do users.  I've seen well performing Confluence systems which work great for the users with thousands of project spaces and then hundreds more spaces for non-project stuff. 

Brent July 26, 2017

I've found that smaller projects are burdensome to require their individual Space.  It gives people far too many places to look to find information.  We've found a balance between project size and Confluence Spaces.  Thus, if I was managing 65 projects, perhaps only 30 would have their own space while the other 35 "small" projects would be under a more generic, category-driven, or team-centric Spaces.

Josie Belliard July 26, 2017

In my opinion, if you create unnecessary spaces, it becomes harder to manage everything. If you use macros you will be able to create a friendly interface for your users. I think the only problem wih Confluence when building large projects is the menu. To compensate for the shortcomings of the navigation capabilities provided by confluence you could by a macro menu, but it can get expensive if you have a large group (each seat pays the fee). On the other hand, if you decide to do it in CSS you might run into other problems, such as security.

Jonathan Smith
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 20, 2018

Martin,

  We have about 60+ active projects in our IT environment. Each is it's own space.

The most important part of these projects is the project status section on the home pages. We wrap this table with the page properties macro so the content will display elsewhere in a nice project dashboard.

Having 60+ projects in one space is do-able, but it would be a page restriction nightmare.

Cheers!

Like # people like this
Kathy Adams January 17, 2019

I'd be interested in what your dashboard tracks and what it looks like.  Is it the widgets from Jira?

Jonathan Smith
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 21, 2019

@Kathy Adams 

  All of our projects are in Confluence currently.

Since we want to keep the table's formatting, it was decided to wrap the table with the excerpt macro, then use the "excerpt include macro" on a project dashboard page. The excerpt include would look for a specific tag within all of the projects and pull in those tables.

This might not be the best method, but it was the best solution at the time for our needs.

zz.jpg

Like Aude Cozens likes this
Jonathan Smith
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 6, 2019

I know this is an old post, but good to keep it up to date :)

Here is another method of tracking sprints / phases in project spaces.

Wrap page properties macro around both project status tables (if multiple). Page properties report would then expose both tables.

Rename title to Project on page properties report page.

a.jpg

Like Sumesh Sukumaran likes this

Comment

Log in or Sign up to comment