Disable bamboo deployment environment tasks?

Hi Bamboo Users,

 

Is there a way to disable one out of a few Bamboo deployment environment tasks?

 

Eg.

Deployment Plan

   -Env1

       --Step1.1

       --Step1.2

   -Env2

      --Step2.1

      – Step2.2

Is it possible to disable only Step 2.2 for example keeping the rest active?

Regards,

Innocentspirit

1 answer

1 accepted

1 votes

Sure, you can do it from UI.

There is no REST API for it

Thanks Alexey for your response - I can't seem to find a way using the UI and hence my question. Using Bamboo Server 5.9.4 here.

Capture 2016-06-04 at 10.30.27.png

Highlighted checkbox allows you to disable task

Thanks Alexey - Sorry I must be going blind - found it now.

 

Suggest an answer

Log in or Join to answer
Community showcase
Renan Battaglin
Published May 18, 2017 in Bamboo

FAQ: How to Upgrade Bamboo Server

Bamboo 5.9 will no longer be supported after June 12, 2017. What does this mean? As part of our End of Life policy, Atlassian supports major versions for two years after the first major iteratio...

1,072 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot