Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Want to Calculate Original Estimate

Edited

Hi,

Whenever I put any remaining time in the parent task and log some work in Its child task it will not cover the remaining time in the parent task but add the logged time in it. What I want when I will set the remaining time in the parent task to 24 hrs and when any work hours will be logged in its child task it will subtract the remaining time from the parent task.

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Mar 12, 2023

Hi @Muhammad Moazzam Hassan 

What do you mean by "parent task" and "child task"?  Specifically, what are the issue types and relationships between those?  Knowing that may help the community to offer suggestions.

And...do you already have an automation rule performing some type of updates for these issues?  If so, please post images of the complete rule and audit log details showing the execution.  Thanks!

Kind regards,
Bill

Hi @Bill Sheboy ,

Thank you for your response. My issue type is a task and the sub-issue type is a subtask. However, I have found the solution.

Solution: Whenever any work is logged in the child task it will automatically subtract the sub-task time logged from the parent task's remaining time.

Like Bill Sheboy likes this