Hi all,
I've implemented this solution (https://community.atlassian.com/t5/Automation-questions/How-do-you-sum-up-story-points-to-the-epic-using-jira-automation/qaq-p/1731595?utm_campaign=&utm_content=post&utm_medium=email&utm_source=atlcomm) and it works great! I use a field title "Story Point Rollup."
I'd like to enhance this and update "Story Point Rollup" when an issue is completed or cancelled. Not sure how to do this, though.
Any help is appreciated.
Thank you!
You will have to change the trigger. Instead of field value changed it will be issue transitioned. Then you can use one of the following rules outlined here to branch to the epic and update the values: https://community.atlassian.com/t5/Automation-discussions/Jira-Automation-Complete-Video-Guides-on-how-to-Sum-Up-Story/m-p/1741948#M75
Regards