You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi all,
I've implemented this solution (https://community.atlassian.com/t5/Automation-questions/How-do-you-sum-up-story-points-to-the-epic-using-jira-automation/qaq-p/1731595?utm_campaign=&utm_content=post&utm_medium=email&utm_source=atlcomm) and it works great! I use a field title "Story Point Rollup."
I'd like to enhance this and update "Story Point Rollup" when an issue is completed or cancelled. Not sure how to do this, though.
Any help is appreciated.
Thank you!
You will have to change the trigger. Instead of field value changed it will be issue transitioned. Then you can use one of the following rules outlined here to branch to the epic and update the values: https://community.atlassian.com/t5/Automation-discussions/Jira-Automation-Complete-Video-Guides-on-how-to-Sum-Up-Story/m-p/1741948#M75