How to create an automation that edits Fix Version when a Sprint is started?

Nyssa Watkin
Contributor
October 7, 2020

Hi I'm looking for some help in creating an automation for the following:

If an issue is in a Sprint and that Sprint is started I want to populate the Fix Version with the latest unreleased version (or a specific version). 

Some things to note about our set up:

We have Squads that work across multiple Projects - but all of these projects share the same Cross-Project Release which I want populated with the Fix Version.

I have tried setting this up and get an error saying:

"The rule has been configured with components that require issues to be provided by the trigger. To run these components you must add a branch for this sprint or JQL. The following components require issues: Issue condition, Edit issue"

Here's what I've got:

Capture.PNG

1 answer

1 accepted

2 votes
Answer accepted
Kristin Lyons
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 7, 2020

Set it up like this:

 

Screen Shot 2020-10-07 at 3.19.47 PM.png

Nyssa Watkin
Contributor
October 13, 2020

Yes, that worked! Thanks so much.

Like rguzman likes this